Question:

How long does a Dependent Verification project take?

Answer:

Traditionally a DEV project takes around 90 days. There are three phases, each 30 days (roughly):

  • Phase 1: Implementation – creating the project plan, communications, video, web portals, census files, internal announcement, more
  • Phase 2: Document collection – process documents, customer service, back and forth with employees about how to finish the requirement, incentive programs, more
  • Phase 3: Grace Period and Close – grace period for late submissions, outbound calls, chasing stragglers, appeals processing, carrier reporting, more